Project Name
45000m3/h HCL tail gas scrubber
25000m3/h HCL scrubber
Location Daman, Saudi Arabia
Time
November, 2014
Client
Steel wire rope manufacturer
Scope of work
EPC PCC provides EPC service, including process engineering design, pipe match, equipment design & manufacture, electrical appliance & meter installation, site installation guidance, commissioning and startup, training etc.
Description
The client provided the tail gas component and the local emission requirements. The discharge tail gas content is much lower than local emission standard This project was delivered within 45 days,finished installation and commissioning in 5 days.
Evaluation
The plant is running stably since started in November, 2014. The client is very satisfied, and develop long term cooperation with PCC.
As one of modular refinery suppliers, we will do our best to meet all the needs of customers.